GageMakkal › Help › How to send equipment out for calibration

How to send equipment out for calibration

At Northwind Precision's Galway plant, a multimeter leaves for the lab. Record it going out, and know where it is.

Video, 1 min 1 s, in English. The steps are written out below.

Steps

  1. Overview → Due dates

    Start on the Overview. Open the due dates to see what is coming.

  2. Open the piece

    Open the piece that is leaving.

  3. Send out

    Choose Send out, pick the supplier and the expected return date, and add a note.

  4. The timeline

    The timeline now shows it away, and when it is expected back.

Good to know: A piece of equipment

  • Record a calibration from here: the next due date is worked out from the interval.
  • A piece follows its equipment type for who calibrates it and how often. Give it its own value, with a reason, only where it really differs.
  • Drag a certificate onto the page: press Analyze and it is read, matched to the piece it is about, and shown to you before anything is recorded.
  • Move the piece to another location and its earlier places stay in its history.
  • In MainteMakkal: Meters shows its running hours (or strokes, kilometres) and their latest readings. Anyone, operators too, adds a reading; a reading can’t be less than the last one. Planners add meters; a plan due by a meter adds its own.